Rebuilding the Foundation for Business-Critical IT

Security, access control, cooling and facilities rehabilitation coordinated around a live IT environment, from procurement through commissioning and handover.

Project scope
IT communications room in Nigeria
Business goal
Rehabilitate a secure, monitored and properly equipped IT room while the facility continued operating.
Server racks lining a bright data-centre aisle.
The organisation

About the client

An organisation required rehabilitation of an IT communications room at an operational Nigerian facility. The engagement combined physical security, equipment protection, cooling and building works within a live working environment.

The business need

The challenge

The room’s weaknesses crossed several disciplines: surveillance, access control, fire-resistant separation, equipment housing and cooling. These workstreams had to be coordinated across suppliers and trades while the surrounding facility continued operating.

What Emocom delivered

Implementation & delivery

Emocom planned and coordinated the rehabilitation from procurement and installation through commissioning and handover, bringing security systems, specialist glazing, cooling and civil works into one delivery scope.

  • Surveillance and remote monitoring

    Installed CCTV surveillance with a network video recorder and secure remote viewing from head office over VPN, linking local monitoring with central oversight.

  • Controlled access

    Implemented card-based access control to restrict entry to authorised personnel and strengthen physical protection of the IT environment.

  • Fire-resistant separation

    Coordinated a fire-resistant glass partition and door, confirming the specification with the client representative and glazier before fabrication.

  • Equipment installation

    Installed the equipment rack as part of the room’s wider rehabilitation, coordinating equipment housing with the surrounding facilities work.

  • Cooling rehabilitation

    Coordinated relocation and recovery of the air-conditioning units, addressing cooling as a dependency of the rehabilitated IT environment.

  • Civil works and finishing

    Managed civil works, painting and cleaning alongside the specialist installations, bringing the room through finishing and commissioning before handover.

  • Integration assessment

    Evaluated CCTV and access-control devices for potential integration with the client’s DCIM platform. This was an integration assessment, rather than a claim of completed DCIM integration.

The outcome

The results

The rehabilitated IT room combined controlled access, CCTV with secure remote viewing, cooling and protected equipment housing. Commissioning issues were resolved before handover, bringing the facilities and security work together in an operational environment.

For similar projects Any organisation rehabilitating a live IT facility needs to coordinate physical security, cooling, equipment protection and commissioning around ongoing operations.

Explore Data Centre & IT Infrastructure
Sources & publication context

Client identities are withheld. Images illustrate the service and do not identify client premises or installations.

Based on Emocom’s supplied project account. Client identity is withheld. The case describes the confirmed scope; no unreported performance figures or financial savings are claimed.